Tattoo Artists
Fulfilling the designer’s vision involved shipping equipment in thirty-five 12m trailers and providing an average of 40 on site staff every day for the three week build. Our construction list included support for a two storey, 800 guest hospitality suite; a self-supporting 300m peripheral handrail; a seemingly solid 4m x 120m back wall complete with 16 secret 2.9m high doors all controlled by Qmotion – as were the two trucking stages supporting Jumbotron video walls.